Building Works · 1 November 2026

Sockets and Switches Inside Built-In Cabinets on a Landed A&A: Settle the Positions Before the Carpenter Measures

Sockets and Switches Inside Built-In Cabinets on a Landed A&A: Settle the Positions Before the Carpenter Measures

Pictured above: the inside of a built-in cabinet on our landed A&A job 37EW, with four switches already fixed to the fabric-lined back panel. A loose board rests on the base and the door hinge is in place. The site update that records these switches going in is dated 8 October, about three weeks after the cabinet carcasses were first noted on site. By that point the position of every switch and socket inside it has to be settled.

When a landed house is rewired, everybody remembers the walls. Owners walk the shell with tape, mark where the sockets go, and the electrician works to that. Cabinets are different, and they catch people out. A built-in cabinet is a box that arrives after the walls are finished, and the power for it is fixed to the box, not to the wall. If nobody wrote down where it should go, the person who ends up deciding is whoever happens to be holding the drill on the day.

This article is about the sockets, switches and cables that live inside built-in cabinets, wardrobes, console units and kitchen carpentry on a landed A&A, and about the one short piece of paper that settles them before the carpenter measures anything.

Why a cabinet is not the same as a wall

On a wall, a socket sits in a box buried in the plaster. The electrician fixes it before the wall is finished and everyone can see where it is. In a cabinet there are three differences.

  1. The cabinet is made after the wall is finished. The carpenter measures from the finished wall, floor and ceiling, not from the drawing. Anything the electrician left in the wall has to line up with a box that did not exist yet.
  2. The surface you fix to is a thin panel, not a wall. A switch or socket needs something to sit in. How it is fixed to a panel is a different question from how it is fixed to blockwork.
  3. The cabinet hides the result. Once the doors close and the shelves go in, a wrongly placed socket is hidden, not fixed. It shows up months later as a charger cable trailing through a door.

The two moments the electrical work happens

On a landed A&A, power to a cabinet is done in two stages, and the site updates for 37EW show both of them.

First, the cable is left where the cabinet will stand. Before the walls and ceiling are closed, cable and conduit are run to the place the cabinet is going. In our photographs of 37EW, a drywall alcove shows a loose cable coiled on the floor, and a cabinet shows a coil of grey flexible conduit sitting inside it. That is what this stage looks like: the supply is there, but nothing is fixed to anything yet.

Second, after the carcass is in, the switches and sockets go on. The site updates of 17 and 22 September record the cabinet carcasses, and on 22 September the island base too, on site and being fitted with the floor still covered. The update of 8 October records the sockets and switches going into the new cabinets, with the suspended ceiling framing up and drywall and corner beads closing in the rooms. That is about three weeks after the carcasses arrived, and it is the order you want: the box first, then the power.

The gap between those two moments is where mistakes happen. A cable left in the wall at the wrong height will not reach a socket in the right place on the cabinet. A cabinet cut for a socket nobody has told the electrician about will not match the cable. That is why the decision has to be made before the first stage, written down, and then passed to both the carpenter and the electrician.

Who does what

Keep the roles separate, because it is the quickest way to find out who is responsible when something is wrong.

  • The carpenter makes the cabinet and makes the openings in the panel for each switch and socket. The carpenter does not connect any wiring.
  • A licensed electrical worker runs and connects the wiring and fixes the switches and sockets. In our earlier article on rewiring a landed house, we described electrical work of this kind as the province of a licensed electrical worker. That does not change because the socket is inside a wardrobe.
  • The builder holds the sequence and makes sure the two have the same drawing. At Wong Lye (BCA General Builder Class 2) that coordination sits with the builder, because the carpenter and the electrician work to different drawings unless someone gives them the same one.
  • You decide what is going to be plugged in and where you will stand when you do it. Nobody else knows that.

Which cabinets need power at all

Go through the house room by room and ask what is going to be plugged in or switched on inside each piece of carpentry. These are the ones that are most often missed:

  • A TV or console unit. Power for the screen, the box, the speaker and the router, and a way for the cables to get from one compartment to another.
  • A pantry or appliance nook. Rice cooker, kettle, coffee machine, toaster. Count the ones that will be on at the same time, and tell the electrician.
  • A wardrobe or shoe cabinet. An internal light with its switch, and a socket for a steamer, a charger or a dehumidifier if you want one.
  • A kitchen island or a bar counter. Sockets for small appliances on the working side, and a decision about whether you want one on the seating side.
  • Any cabinet with lighting. Strip lights inside shelves need a switch, and may need a driver. Where does the driver sit, and how will anyone reach it later?

If a cabinet is on that list and nobody has said where its power comes from, the position has not been decided.

The one-page schedule that settles it

Ask for a single page, one line per cabinet, signed off before the carpenter starts. It does not need to be fancy. For each cabinet it should say:

  1. Which cabinet it is, using the name on the carpentry drawing.
  2. What will be plugged in or switched on inside it.
  3. How many sockets and switches, and which side of the cabinet each goes on.
  4. The height of each one measured up from the finished floor, not from the bottom of the cabinet. A cabinet may stand on a plinth or a kick board, and the two measurements will not agree.
  5. Where the cable comes in: from the wall behind, from the ceiling above, or from the floor.
  6. For any light, which switch controls it and where that switch is.

Then both the carpenter and the electrician get the same page. If they disagree about a number, the disagreement shows up on paper, in October, instead of on site in November with the panels already cut.

The panel has to take the fitting

A switch or socket needs a box or a mounting that suits the panel it is fixed to. A cabinet back or side is a thin panel, so ask the carpenter and the electrician, before the cabinet is made, which kind of mounting each position will use: one set into the panel, or one fixed on the surface. It affects how the opening is cut and how deep the space behind the panel needs to be. The carpenter should not be guessing at the size of the opening, and the electrician should not be enlarging it with a saw once the cabinet is laminated.

Ask also whether the opening is cut in the workshop or on site. A hole cut into a finished, laminated panel cannot be un-cut. If it is in the wrong place, the panel is replaced.

Heat, water and reach

Three small questions catch most of the problems that appear after handover.

  • Heat. A charger, a router or a light driver gives off warmth and wants air around it. Ask where each one will sit inside the cabinet and whether that space has room for it to breathe. The same reasoning applies to a cupboard in a humid house, which we covered in the article on the door under the staircase.
  • Water. A cabinet next to a sink, or any cabinet in a bathroom, is a different case from a bedroom wardrobe. Ask the electrician what the fitting has to be rated for. Do not guess, and do not let the carpenter choose.
  • Reach. After the shelves are in, can you actually get a plug into that socket? A socket behind a fixed shelf is a socket nobody uses. And if a driver or a connection ever fails, can the electrician get to it without taking the cabinet apart?

Photograph it before it closes

Ask for a photograph of each wall or panel at the stage where the cable is left, with a tape measure in the frame showing the height from the floor. It costs ten seconds on site. Months later, when a drill is about to go into a wall or a panel, that photograph is what tells you what is behind it. It is the same reasoning as in our article on deciding the electrical layout before the walls close: the cheap moment to get it right is before anything is covered.

Where this sits in the finishing stage

Cabinet power is a finishing-stage item that has to be decided much earlier than it looks. The trade order for the last weeks of a landed A&A, and the lead times that hold it up, are set out in the finishing stage of a landed A&A, and the same ordering logic applies here: the cabinet is made after the walls, the power is fixed after the cabinet, and the floor stays covered until the last of them is done. Our page on the finishing stage of a landed A&A sets out how we run that stage.

We publish dated photographs from current jobs on the Live Jobs page, with the captions as they were written on site, so you can see the carcass and the switches arrive in that order on a real job rather than on a drawing.

If you are about to order your carpentry

Send us the address, the type of house and the carpentry drawings if you have them, and we will go through which cabinets need power and what the schedule should say. We give a quotation after seeing the plot and the drawings, not before. See our landed A&A works page for the full range of work we take on.

The same habit applies in a wet wall. See settling the shower niche, hooks and holders before the tiler starts.

WhatsApp us on 9107 2601

Outdoors the same rule holds: see where the gate pillar lamp cable, the outdoor socket and the opening go before the pillar is rendered.

Live jobs

Common questions
Who connects the wiring for sockets and switches inside a built-in cabinet?
A licensed electrical worker connects the wiring and fixes the switches and sockets. The carpenter makes the cabinet and the openings in its panels but does not do any wiring.
When should I decide where the sockets inside my cabinets go?
Before the carpenter measures, and before the cable is left in the wall for the cabinet. Write each position on a one-page schedule and give the same page to the carpenter and the electrician, so that the cable in the wall and the opening in the panel line up.
How should the height of a socket in a cabinet be measured?
Measure up from the finished floor, not from the bottom of the cabinet. A cabinet can stand on a plinth or kick board, and the two measurements will not agree.
Which built-in cabinets usually need power?
TV or console units, pantry and appliance nooks, wardrobes with internal lights, kitchen islands, and any cabinet with strip lighting. If something will be plugged in or switched on inside a cabinet and nobody has said where its power comes from, the position has not been decided.
Can a socket be added to a cabinet after it is made?
Sometimes, but it means cutting into a finished panel and getting a cable to the new position, and a hole in a finished panel cannot be un-cut. Ask before the cabinet is made which positions it needs.
← Back to Journal

Have a Question We Haven't Answered Yet?

Most of our articles start as questions from WhatsApp conversations. If there's something you wish a builder would explain honestly, send it to us.

Send Us a Question →
WhatsApp · Direct line to the builder
Speak to the Builder