Inside a Micropile on a Landed Rebuild: Rebar Cage, Spacers and Grout, and the Records to Ask to See
Pictured above: looking down a freshly drilled micropile hole on our landed reconstruction job 22PS. The steel bars of the rebar cage stand in the hole with a black plastic spacer wired to them, and the hole is full to the brim around them. Once the pile cap and the ground beams are cast over it, nobody will ever see this again.
On a landed rebuild the foundation is the one part of the house that is finished, covered and forgotten within days. The floors, the staircase and the kitchen you will look at for years. The piles you will see for an afternoon, if you happen to be on site, and after that only a photograph can show you what is down there.
This article is about one small pile and the three things that go into it: the rebar cage, the spacers that hold it in place, and the grout. It uses the photographs from job 22PS as the example, and it ends with a short list of records you can ask your builder to show you. You are not expected to judge a pile. You are entitled to ask whether the person who is paid to judge it has seen the evidence.
Who designs the pile, and who builds it
Start with the division of work, because it settles what you can reasonably ask for. The pile is designed by the structural engineer: how many, where, how deep, what bars go in, what grout. The builder's job is to build exactly that, record that it was built, and let the engineer see the records. A General Builder such as Wong Lye (BCA General Builder Class 2) builds what the drawings say. The builder is not the engineer and should not be redesigning a pile on site because it is convenient.
That matters for the question you ask. "Is the pile good?" invites a reassuring answer from anyone. "Which depth did the engineer ask for, which depth was reached, and who confirmed it?" has a factual answer, and it either exists on paper or it does not.
What happens to one micropile, in order
A micropile is a small-diameter drilled pile. Wong Lye's piling and foundation works page lists micropiles among the methods used for tight urban sites, where a larger rig cannot get in or cannot stand. The Live Jobs record for 22PS shows the sequence over several days, pile by pile, with dated photographs and one-line captions. Reading those captions together, one pile goes through these steps:
- Drilling. The rig drills down, adding rods as it goes. One caption for the job reads "S9-2 drilling work started", with the pile heads exposed in the excavated pit around it.
- Depth confirmed. The drilled depth is checked before anything goes in the hole. A photograph from the same stage shows a graduated tape lowered into a hole. The caption for the C13-1 pile records "depth confirmed".
- Rods dismantled, water flushing. The drill rods come out and the hole is flushed with water. The captions list this as its own step, after the depth check.
- Rebar cage installed. The reinforcement goes down the hole as a cage: several vertical bars held in a spiral of binding steel.
- Grouting. The hole is filled with grout. The captions for both piles end with "grouting complete".
None of this is hidden, but it happens inside a pit or behind hoarding, and each step is covered by the next. That is why the record matters more than the visit.
The depth check: the number that matters most
A pile that stops short of the depth on the drawing is a pile that is not carrying what the engineer counted on it to carry, and from the surface there is no way to tell. That is why the depth check is the step to ask about first. What you want to know is simple: the depth shown on the engineer's drawing for that pile, the depth the drill reached, the date, and who took the measurement.
For a job with many piles, ask how that is recorded. The live feed for 22PS describes the job as 30 piles and 17 columns, which is thirty chances for a number to be written down wrongly or not at all. A table with one row per pile number is easy to keep and easy for an engineer to read. A single note saying "all piles to depth" is not the same thing.
The rebar cage and the spacers
The cage is the steel that gives the pile its strength along its length. What is easy to overlook is how it sits in the hole. If the cage rests against one side of the hole, the bars on that side have almost no grout outside them and the bars on the other side have too much. Steel needs grout all around it to be protected and to work with the rest of the pile.
That is the job of the black plastic spacer in the photograph. It is wired onto the bars, and its arms press outward to hold the cage away from the wall of the hole, so that the cage hangs in the middle with grout able to fill the gap on every side. It is a cheap part and a small one, and it is the part that shows whether someone has thought about what happens once the cage disappears down the hole.
You do not need to judge the spacing yourself. You can ask two things: whether the engineer's drawing calls for spacers on the cage, and whether there is a photograph of the cage with them on, taken before it went down the hole. A cage photographed on the ground, spacers in place, takes ten seconds and answers the question for the record.
The grout
Grout is the last step and the one that cannot be undone. Once the hole is filled, the only way to check it is to test it, and the test results come later. Ask what the grout mix is, who mixed it, and what records exist for it. If the engineer asked for grout samples to be taken and tested, ask when the results are due and who receives them. Do not accept "it was fine" as a record of grout.
If something looks wrong on the day, a hole that took far less or far more grout than expected, for example, that is a conversation to have with the engineer on the same day. It is never a reason for the builder to decide on his own that it is acceptable.
Seven records to ask to see
Which records exist depends on your engineer's design and on what has been submitted for your project, so ask your builder and your engineer which ones apply. This is a starting list of things worth asking for, in plain terms:
- A pile plan. Every pile numbered, so that a photograph or a record can be tied to a position on the plot.
- The design depth for each pile, as it appears on the engineer's drawing, next to the depth actually reached.
- The date and the person who confirmed the depth for each pile.
- A photograph of each cage before it goes down, with the spacers visible.
- A note of the grout used for each pile, and the results of any tests the engineer asked for.
- The engineer's acknowledgement that they have seen these records before the pile caps and ground beams cover the heads.
- A copy of all of it, handed to you at the end of the piling stage, not held back until the end of the job.
The last two are the ones that protect you. Records you only see when you ask for them at handover are records that someone may have to reconstruct. Records you were given while the pile heads were still uncovered were made when it was still easy to be accurate.
What to check on a visit, without climbing into the pit
If you are invited onto the site during piling, you do not need to understand the rig. Ask the person running the job to show you the pile plan and the page where depths are being recorded for today's piles. Ask which pile they are on and which ones have been grouted. Ask where the cage photographs are kept. A builder who keeps these records as a routine will answer without hesitation, usually by opening a folder. One who has to go and find them has told you something too.
Where to follow a real job
Wong Lye publishes dated photographs of its current jobs, and the piling stage of 22PS is on the piling on a landed reconstruction page, with every photograph captioned as it came off the site. Two earlier articles cover what comes before and after the drilling: what the surveyor marks and checks before the piling rig arrives, and what gets settled about underground beams and the lift pit while the piling rig is still on site. For the checks that come after the foundation is covered, see the stage checks to ask for before concrete is poured and structure is covered.
If you are planning a rebuild and want to know how piling would be handled on your plot, send us the address, the type of house and anything you already have from a soil investigation. We will tell you what the work involves and what records to expect. We give a quotation after seeing the plot and the engineer's design, not before. See our landed A&A and reconstruction works page for the full range.
Also read: what the bars standing out of the grout at the top of the pile are for, and what to check before the pile cap goes on, in pile tops on a landed rebuild.