Building Works · 9 October 2026

Large-Format Floor Tiles on a Landed A&A: What the Floor Underneath Has to Be Before the First Tile Goes Down

Large-Format Floor Tiles on a Landed A&A: What the Floor Underneath Has to Be Before the First Tile Goes Down

Large tiles look simple on a showroom floor and unforgiving on a real one. A big-format tile is stiff, it does not follow the floor underneath it, and every low spot, high spot or lump of dried cement under it shows up as a rocking tile, a hollow sound, a cracked corner or a lip you catch your toe on. So if you are about to tile a landed A&A with large tiles, the question to ask is not which tile. It is what the floor has to be before the first tile goes down, and who is responsible for making it so.

This post is about that floor: the slab, the screed on it, the falls where water has to leave, and the checks you can make yourself before the tiler is booked in. We build landed A&A works, so the examples are the stage we see on our own sites, including the tiling updates we posted from 37EW, a three-storey semi-detached house, on our live jobs page.

Large tiles do not hide anything

A small tile or a mosaic can ride over a slightly uneven bed because there are many joints to absorb it. A large tile has few joints and a lot of unsupported area. If the bed under it is not flat, it is supported on its high points and hangs over its low ones. Walk on it a few months later and that is where it cracks, or where the grout line opens up.

That is why the work that decides how a large-tile floor turns out happens before any tile is in the house. The tiler gets the blame for what is under the tile, because the tiler is the last person to touch it, and that is exactly why you want the floor settled in writing with your builder first.

The order on a real job: screed first, then tiles that follow the fall

On 37EW, our own update for the courtyard says it plainly: every gradient is measured so water runs off the way it should, the screed bed goes down first, then the tiles follow the fall. Another update on the same job says levels were checked as the work went on. Those two sentences are the whole discipline. The screed makes the floor flat and sets the slope. The tile then copies it.

Inside the house the screed is there to flatten, and outside it is there to flatten and to slope as well. In a bathroom, a balcony, a courtyard or a car porch, the floor has to fall towards the drain or the edge, and that fall has to be built into the bed, not hoped for in the adhesive. A tile laid dead flat across an area that was supposed to drain gives you standing water that no amount of grout will fix.

Two things follow from this for an owner:

  • Ask where the falls are. For every wet or external area, ask your builder where the water is meant to go and how the slope is being set. If the answer is vague, the tiling date is too early.
  • Do not let the tile choice change the plan late. A thicker or larger tile than the one the floor was prepared for changes the finished height at doors, at stair landings and where the tiled floor meets another floor. Fix the tile before the floor levels are set, not after.

What levelling clips do, and what they do not

The orange and black clips in the photo are levelling clips. We use them on large tiles to keep neighbouring tiles at the same height and the joints straight while the adhesive sets. Our updates from 37EW mention them again and again for that reason: they hold alignment and flatness across a big floor.

What they cannot do is rescue a bad bed. A clip pulls adjacent tile edges level with each other, so it stops one tile sitting higher than the next. It does not remove a hump in the floor that all the tiles are sitting on. That is the screed's job. If you see clips on a floor, you are seeing a good habit; it tells you nothing about whether the screed under them is right.

One more point from the same updates is worth copying. Where a floor has access covers or openings for services, the tiles should be cut so the grout lines carry straight through the cover. On 37EW that is how the courtyard covers were done. It is a small detail, and it is the kind of thing that tells you a tiler was planning the layout rather than filling the floor.

Check the slab and screed before the tiler arrives

You do not need instruments. You need to ask for the checks and see them done. Before tiling starts on any area:

  • Is the screed finished and left alone? A screed needs time before it takes a tile, and walking over a fresh one or loading it with materials is how it ends up damaged. Ask your builder how long it will be left and what the programme allows. On 37EW the interior screed went down weeks before the final floor covering, which is normal for the sequence we describe in the finishing stage of a landed A&A.
  • Is it flat? Ask to see a long straightedge or a level laid across it in a few directions. A gap you can slide a finger under is a low spot to fix now.
  • Is it clean and sound? No loose crumbling surface, no dust, no old adhesive or paint splash. The adhesive can only grip what is actually solid.
  • Is the waterproofing done and tested where it applies? In wet areas the membrane goes in before the screed or tiles that cover it, and it should be proved before it is hidden. Water found in the room below after the tiles are down means breaking the floor. Where this goes wrong is in waterproofing failure points on landed homes.
  • Are the drains, floor traps and openings in the right place, at the right height? Move a floor trap after the tiles are laid and you have cut through your own work.

After the tiles are down: how to find a problem early

You can test a floor yourself at handover, and it is much cheaper to find problems while the builder is still on site. Walk it slowly. Tap tiles with a coin or the back of a knuckle: a hollow, drummy sound against a dull solid one means the adhesive has not filled behind the tile. Run your foot over the joints and feel for lips. Look along the floor from a low angle with a window or lamp behind you; ripples and uneven lines show up in the reflection. Pour a little water on any tiled area that is supposed to drain and watch which way it goes.

Write what you find on the defects list and photograph it. The room-by-room walk is set out in handover and the defects inspection, room by room. A hollow tile found in the first walk is a replacement. The same tile found a year later, with a crack across it and a disagreement about whose fault it is, is a much longer conversation.

Pay for tiles that are laid, not tiles that are stacked

Boxes of tiles stacked in the porch are not a tiled floor, and a sensible payment schedule says so. The tiling payment should be tied to areas that are laid, levelled and checked. We cover the wording in progress payments on a landed A&A.

Questions to ask before you choose the tile

  • What size and thickness is the tile, and has the floor been set out for it?
  • How is the floor being flattened, and who checks it before tiling starts?
  • Where are the falls in each wet or external area, and where does the water go?
  • Is the waterproofing in those areas tested before it is covered?
  • How will the tiles be cut around floor traps and covers so the joints stay straight?
  • What happens to the finished floor height at each door and landing?
  • When is the tile delivered, and where is it stored until it is laid?

Talk to us

If you are planning a landed A&A and want a second pair of eyes on the floor, the tile and the sequence, WhatsApp us on 9107 2601 and tell us about your house and where the project is up to. Wong Lye Pte Ltd holds a BCA General Builder Class 2 (GB2) licence and builds A&A works, extensions and reconstructions on landed homes. See A&A works for landed homes.

Related reading: the finishing stage of a landed A&A · waterproofing failure points on landed homes · handover and the defects inspection, room by room

The same large, glossy, marble-look finish goes on walls too: see a marble-look feature wall in a landed house: what the wall behind it must be.

If you are choosing vinyl instead of tile in some rooms, the base matters just as much. See what the screed must be before vinyl goes down.

Live jobs

Common questions
What does the floor need to be like before large-format tiles are laid?
The screed should be finished, flat, clean and sound, with the falls for wet and external areas built into the bed. A large tile is stiff and bridges low spots, so an uneven floor shows up later as rocking, hollow or cracked tiles.
Do levelling clips fix an uneven floor?
No. Levelling clips keep neighbouring tile edges at the same height and the joints straight while the adhesive sets. They cannot remove a hump or dip in the screed underneath, which is a separate job done before tiling.
Why do tiled courtyards and balconies need a screed with falls?
Water has to run to the drain or the edge. On our 37EW courtyard job the screed bed went down first and the tiles followed the fall, with gradients measured so water runs off. Laid dead flat, an area that should drain holds standing water.
How can I check tiling for hollow spots after it is laid?
Tap tiles with a coin or a knuckle and listen for a hollow, drummy sound compared with a dull solid one. Feel across the joints for lips, look along the floor at a low angle for ripples, and pour a little water on areas meant to drain. Write findings on the defects list and photograph them.
Should I pay for tiles when they are delivered?
Pay for areas that are laid, levelled and checked, not for boxes stacked on site. Delivered is not installed, so ask for the tiling payment to be tied to finished areas.
← Back to Journal

Have a Question We Haven't Answered Yet?

Most of our articles start as questions from WhatsApp conversations. If there's something you wish a builder would explain honestly, send it to us.

Send Us a Question →
WhatsApp · Direct line to the builder
Speak to the Builder