Formwork and Rebar for a Lift Structure in an Existing Landed House: What the Box Has to Hold and What to Look at the Day Before the Pour
Pictured above: a new reinforcement cage for the lift structure on our landed job 17CBR, standing against the chipped-back face of the old wall, with a dark formwork panel on its other side and scaffold poles beside it. Our site update of 4 November on the Live Jobs page says rebar and formwork are going in for the lift structure.
Most owners who add a lift to an existing house think about the lift itself: the model, the finish, the door. The part that decides whether the lift can be installed at all is a concrete box, and the box is made inside another box. The inner one is called formwork, it is temporary, and it is gone within days. But whatever shape it holds when the concrete is poured is the shape your lift has to live with for the life of the house.
This post is about that moment on a lift structure in an existing landed house: what the reinforcement and formwork are doing, why an old house makes it harder than a new one, and what you can ask to see the day before the pour. It follows what our own 17CBR updates show.
What the 17CBR updates record, in order
17CBR is an addition and alteration job on an existing three-storey semi-detached house. These are the entries from our own updates, so you can see the order of work rather than take our word for it.
- 29 August. The Permit to Commence Work is in. Our update says it took months of applications and rejections to get there, and that work can start on site.
- 16 September. Lift shaft work has started. The floor slab has been opened up, with scaffold barriers around the opening, and the steel reinforcement bars and mesh are on site.
- 29 September. Columns are up, the rebar mesh is in place, and the update says engineers have done a thorough check.
- 4 November. Rebar and formwork are going in for the lift structure.
Two things stand out. The permit came first and the steel was on site before the structure was cast, so by the time the formwork goes up, most of the questions should already have been answered on paper. And the formwork is one of the last steps before concrete, not the first. Everything before it is about making the house safe to cut into. We have not posted the pour for this structure yet, and we are not going to guess the date here.
What formwork is actually for
Concrete goes in as a heavy liquid. Until it hardens it has to be held in the exact shape it will keep, and it pushes outwards on whatever holds it. Formwork is that holder: panels, with props and bracing that stop them moving. In the photo above the dark panel is the face of the formwork. When it is taken away, the concrete that was against it is the surface of your shaft wall.
That is the part owners do not expect. In a lift shaft the formed face is not a rough surface that will be hidden. It is the face the lift installer measures against and fixes to. The lift supplier's shaft specification gives the internal dimensions, the pit depth, the headroom, the door openings and the fixing points. We said in our post on adding a home lift to an existing landed house that most lift jobs that go wrong go wrong at the line between the shaft the builder delivers and the shaft the supplier specified. The formwork is where that line is drawn, physically, in plywood and props.
Why an old house makes it harder
In a new building the box is formed in clear space. In an existing house, one face of the box is the old wall, and you cannot order that wall to a size.
- The old face is chipped back to sound material. In the photo the old wall on the left has been cut back and the surface is rough and uneven. The new concrete has to bond to what is left, so what is left has to be solid. If the chipping stops at loose material, the new work is only as good as that.
- Bars come out of the old wall. The short bars you can see sticking out of the cut face are what tie the new structure to the old one. We explained how that works in how new concrete ties into the old slab and brick. The point for this post is that the formwork has to be built around those bars without bending or moving them.
- The joint between panel and old wall has to be tight. Where wet concrete finds a gap it runs out through it, and what is left behind is rough, stony concrete at the edge. On a lift shaft that edge is exactly where the supplier needs a clean, true line.
- Everything is propped off a house that is still standing. The scaffold in the photo is part of that. Props need a base that will not move while the concrete goes in, and in an old house that base has to be chosen, not assumed.
What the steel is doing, and why the formwork matters to it
The reinforcement is the cage of bars and links you can see tied together in the photo. The concrete resists being squashed; the steel resists being pulled apart. The structural engineer decides which bars go where, and the site has to match the drawing for that element.
The formwork matters to the steel in one specific way. The bars must sit inside the concrete, with concrete all around them, and not touch the panel. Steel that touches the formwork ends up at the surface of the finished wall, where it can rust and mark. The usual way to prevent that is with small spacers that hold the cage off the panel, so asking whether they are in is a fair question. We covered the same idea for piles in our post on the rebar cage, spacers and grout in a micropile.
What to ask to see the day before the pour
You do not have to judge the bars or the props yourself. You do have to make sure the check happens, by someone qualified, before the concrete covers it. Here is what we would ask for on a lift structure in an existing house.
- The lift supplier's shaft drawing, on site, next to the formwork. The shaft should be built to the model you have chosen, not to a placeholder. If the model is not chosen yet, the pour is early.
- The plaster question. Ask whether the formed face is the finished face, or whether plaster or a lining will go on it. If something goes on it, it takes up space inside the shaft, and the formwork has to allow for it.
- Openings formed, not cut later. Door openings and any holes the lift supplier needs are boxed out in the formwork before the pour. Cutting them afterwards in a structural wall is a structural job in its own right.
- Dated photos of the cage with the element named. A photo of "some rebar" proves nothing. We said the same in our post on stage checks before concrete is poured: ask who looked at it before the pour, and have a name and a date.
- The engineer has seen it. The person whose design the site must match should have had the chance to look before the pour goes ahead. Ask for that in writing. The 29 September update on this job records an engineers' check at the earlier stage; ask for the same at this one.
- The bottom of the box is clean and dry. Tie-wire offcuts, debris and standing water at the bottom of a lift pit end up inside the concrete. A pit in Singapore ground collects water, as we said in our post on the lift pit and underground beams, so the cleaning has to be the last thing done before the pour, not the first.
- The panels are tight, braced and propped. Look for gaps between panels and at the old wall. Ask who is responsible for watching the formwork while the concrete goes in.
Also ask for one thing that is easy to forget: how long the formwork stays up after the pour, and who decides when it comes down. Taking it off early to see how the concrete turned out is the wrong way round.
What we will not give you here
We do not put a price on a lift structure on a website. It depends on the house, the lift model and what the old structure turns out to be once it is opened, and the supplier's specification has to come first. We quote after a site visit and a look at the drawings. We also will not tell you how many days any step takes on your house. The updates above are the dates on one job.
The honest limit of one job
17CBR is one three-storey semi-detached house. A detached house, a terrace, a different shaft position or a lift with a different specification will change the order and the detail. What carries over is the sequence of questions: which lift, built to which drawing, checked by whom, before what is covered. If the order on your job is different, ask why.
Next step
If you are planning a lift in an existing landed house, start with our A&A works for landed homes page. For the wider picture, read adding a home lift to an existing landed house: the shaft, the pit and the approvals. Or send us the house type, the stage you are at and whether the lift model is chosen on WhatsApp, and we will tell you what we would settle before the formwork goes up.