Landed A&A Project: The Stage Checks to Ask For Before Concrete Is Poured and Structure Is Covered
On a landed A&A, the most important parts of the job are the ones you will never see again. Reinforcement disappears into concrete. Steel connections get boxed in. Waterproofing goes under screed, and pipes and wiring go behind walls. Once that happens, the only evidence of what was done is whatever was recorded at the time.
That is why a good A&A project is organised around stages, not just around a finish date. Each stage has a moment just before it gets covered, and that moment is the cheapest time in the whole project to find a mistake. This guide is about that moment: what is worth looking at, who should be looking, and what to ask for so the answer is on paper rather than in someone's memory. It is reader guidance, not a legal checklist. Where a requirement depends on your property, your appointed professional will tell you which stages apply.
Why the covered-up stage is where owners lose the most
A defect in a finish is visible the day you move in. A defect inside the structure can sit quietly for years. The owner's real exposure is not that builders are careless, it is that nobody can easily check something after the fact without opening it up.
This also connects to your warranty. On a landed home, the seven-year warranty on Wong Lye's A&A works answers a structural fault in what we built, and it is written item by item in the quotation. It does not cover existing structure we did not touch, and it does not cover the joint where a new extension meets your existing house. That joint is exactly the kind of place where a dated record matters, because it sits between what is new and what is old. We cover the terms in your warranty after handover.
Who should be doing the checking
Three different parties can be looking at a stage, and they are not interchangeable.
- The builder checks its own work as it goes. That is necessary, but it is the party being checked, so it cannot be the only one.
- Your appointed professional. On a landed A&A the URA and BCA submissions are made by a QP, meaning the architect or the professional engineer, not by the builder. For structural work, the structural engineer is the person whose design the site must match. Wong Lye coordinates the architect and structural engineer as part of one quotation, so drawings, submissions including structural certification, and the build sit with one accountable party.
- You. You are not expected to read a reinforcement drawing. You are expected to ask whether the right person has looked, and to keep the record.
The single most useful question to ask before you sign is this: "Which stages on my project will be inspected before they are covered, by whom, and can I have that list in writing?" The answer depends on your house, so do not accept a general reassurance. Ask for the list.
Check 1: What was found versus what was drawn
The first stage that matters happens before anything new is built. Old landed houses rarely match their drawings exactly. For homes built before 1990, Wong Lye does a foundation review and a column and beam load calculation before quoting, because older houses were often built to standards that do not anticipate today's heavier loads. If something different from the drawings is found once walls or floors are opened, three things should happen: it is photographed, the structural engineer is told, and the owner gets a written note of what it changes in scope or price.
Ask: "What did you find that differs from the approved plans, and does it change anything?" Do not accept "all fine" without a date and a photo attached to it. If a change follows, it should go through the same written process as any other variation, which we describe in variation orders on a landed build.
Check 2: Reinforcement and formwork, before the concrete goes in
For any new slab, beam, column or foundation, the last chance to see the steel bars is just before the pour. After the pour, nobody can tell by looking whether the bars were the right size, in the right place, or properly covered.
What this stage is about, in plain terms: the bars and formwork should match the structural drawings for that element, and the person responsible for the structural design should have had the opportunity to look before the pour goes ahead. You do not need to judge the bars yourself. You need to know that the check took place.
- Ask for dated photos of the reinforcement with the element identifiable, for example a note on the photo saying which beam or slab it is. A photo of "some rebar" proves nothing.
- Ask who inspected it before the pour, and whether that is recorded. A name and a date are enough.
- Ask whether test samples will be taken from the concrete delivered for your pour, and who keeps the results. Whether testing applies and how it is done for your project is a question for your structural engineer, so ask for the answer in writing.
- Do not agree to a pour being brought forward for convenience before the inspection has happened. A delayed pour costs a day. A missed inspection can cost much more.
Check 3: Where the new structure meets the old
On an extension, the riskiest detail is usually the connection between the new part and the existing house. New and old move differently, finish differently and sometimes settle differently. It is also the detail that most easily gets argued about later, because each side can say the problem started on the other side of the joint.
So treat it as a stage in its own right. Before it is closed in, ask that the joint is photographed, that the structural engineer has seen how it is being formed, and that the drawings show how it should be done. Then agree in writing what the builder is responsible for at that joint and what remains the behaviour of the existing house. We go deeper on this in rear and kitchen extensions: where the new meets the old.
Check 4: Steel connections, before they are coated or boxed in
Many landed A&A jobs use steel: a new beam where a wall came out, a staircase frame, a loft platform, a canopy. The part of a steel frame that does the structural work is the connection, where one member is bolted or welded to another. Once steel is painted, fire-protected or boxed behind plasterboard, the quality of the weld or bolting is hard to judge.
The photo at the top of this page shows a welder at a beam-to-column connection on one of our steel jobs. It is an example of a connection stage, not a landed house. The point for an owner is the order of events: connections are made, looked at by the person responsible for the structural design, and only then coated or covered.
- Ask that connections are checked before paint, fire protection or cladding goes on.
- Ask for dated photos of each main connection, with its location written on the photo.
- Ask who confirms the steel matches the approved drawings, and how that confirmation is recorded.
If the steel will be a mezzanine or loft, the related approvals are in internal lofts and mezzanines in a landed house.
Check 5: Waterproofing and services, before the screed and walls close
Waterproofing failures and buried services are the covered-up defects that owners most often meet in real life, because leaks announce themselves. Roof terraces, bathrooms, planters and any area with a screed over a membrane all belong here.
- Ask that the membrane is checked before it is covered, and that the way it will be tested (for example, holding water on it for an agreed period) is agreed beforehand and the result recorded with a date.
- Ask for photos of pipe and wiring routes before the walls close. We cover the electrical side in rewiring a landed house before the walls close.
Tie each stage to your payment
Wong Lye collects a small deposit, typically 5 to 10 percent of project value, and bills the rest at milestones tied to actual job completion. A stage check gives that arrangement something real to hang on. If a milestone description in the quotation says "reinforced concrete slab completed", then the record for that stage should exist before you pay: the dated reinforcement photo, the inspection note and the pour date. Our guide to the owner's role on site covers the milestone check step by step.
What if something was already covered?
It happens, usually because a pour was brought forward or a photo was not taken. Do not demand that finished work is broken open by reflex. Ask your structural engineer what is proportionate. The answer may be that the available records are enough, or that a non-destructive check is reasonable, or, where there is real doubt, that a small opening is needed. That decision belongs to the professional responsible for the design, not to you or the builder alone. What you should do is write down the date you found out and ask for the decision in writing.
Quick checklist
- Before signing: get the list of stages that will be inspected before they are covered, in writing.
- Existing structure: photos and a written note of anything different from the drawings.
- Before each pour: dated, identifiable photos of the reinforcement, and a record of who inspected.
- Where new meets old: photograph it and agree responsibility in writing before it closes.
- Steel: connections checked before coating, fire protection or cladding.
- Waterproofing and services: checked and recorded before screed and walls close.
- Pay each milestone only when that stage's record exists.
Planning a landed A&A and want to know how each structural stage will be checked and recorded before you commit? WhatsApp us on 9107 2601 and tell us about your house and what you want to build. Wong Lye Pte Ltd holds a BCA General Builder Class 2 (GB2) licence and builds A&A works, extensions and reconstructions on landed homes. See A&A works for landed homes.
Related reading: the owner's role on site · progressive milestone billing · handover inspection
Also read: underground beams and the lift pit on a landed rebuild
Also read: new concrete columns inside an existing house, and how they are tied into the old slab and brick.
Also worth reading: for the piling stage, which is covered by the pile caps, see Inside a Micropile on a Landed Rebuild: Rebar Cage, Spacers and Grout, and the Records to Ask to See.
Also read: the lift structure on a live job: what the formwork and rebar must do before the pour.